Global transmission line length was estimated to have reached 5,465,957Ckm by the end of 2021 and is forecasted to grow to 6,485,343Ckm by 2027. Ghana had 6,471Ckm of line length in 2021 and this is expected to rise to 7,510Ckm by 2027. Listed below are the five largest transmission projects by line length in Ghana, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission line segment. Buy the latest transmission line project profiles here.

1. A4BSP – Kumasi Line

The A4BSP – Kumasi Line is a 330kV overheadAcccra IV Bulk Supply Point, Pokuase to Kumasi. The project is planned and is expected to be commissioned in 2023.

The A4BSP – Kumasi Line is an overhead line that will be operated by Ghana Grid. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

2. Aboadze – A4BSP Line

The Aboadze – A4BSP Line is a 330kV overheadAboadze to Acccra IV Bulk Supply Point, Pokuase. The project is planned and is expected to be commissioned in 2023.

The Aboadze – A4BSP Line is an overhead line that will be operated by Ghana Grid. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

3. Aboadze – Prestea – Kumasi Line

The Aboadze – Prestea – Kumasi Line is a 330kV overheadAboadze to Kumasi. The project is under construction and is expected to be commissioned in 2023.

The Aboadze – Prestea – Kumasi Line is an overhead line that will be operated by Ghana Grid. The line will carry alternating current (AC) Buy the profile here.

4. Anwomaso – Kintampo Line

The Anwomaso – Kintampo Line is a 330kV overheadAnwomaso to Kintampo. The project is under construction and is expected to be commissioned in 2023.

The Anwomaso – Kintampo Line is an overhead line that will be operated by Ghana Grid. The line will carry alternating current (AC) Buy the profile here.

5. Prestea – Dunkwa – Kumasi LIne

The Prestea – Dunkwa – Kumasi LIne is a 330kV overheadPrestea to Kumasi. The project is planned and is expected to be commissioned in 2023.

The Prestea – Dunkwa – Kumasi LIne is an overhead line that will be operated by Ghana Grid. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

For more details on the latest transmission line projects, buy the project profiles here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying data, research, and analysis used to produce this article.

GlobalData’s Power Intelligence Center provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide, while its capacity and generation database provides historic and forecast power generation and generation capacity by technology as well as consumption, imports and exports for over 170 countries.