Global transmission line length was estimated to have reached 5,465,957Ckm, while Mozambique had 6,456Ckm of line length by the end of 2021. Listed below are the five largest transmission projects by line length in Mozambique, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission line segment. Buy the latest transmission line project profiles here.

1. Cataxa – Maputo Line

The Cataxa – Maputo Line is a 500kV overheadCataxa to Maputo. The project is under construction and is expected to be commissioned in 2024.

The Cataxa – Maputo Line is an overhead line that will be operated by Electricidade de Mocambique EP. The line will carry direct current (DC) through double circuit cable. Buy the profile here.

2. Caia – Nacala Line

The Caia – Nacala Line is a 400kV overhead line with a length of 800Ckm running from Caia to Nacala. The project is under construction and is expected to be commissioned in 2023.

The Caia – Nacala Line is an overhead line that will be operated by Electricidade de Mocambique EP. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

3. Chimuara – Alto Molocue Line

The Chimuara – Alto Molocue Line is a 400kV overhead line with a length of 340Ckm running from Chimuara to Alto Molocue. The project is under construction and is expected to be commissioned in 2024.

The Chimuara – Alto Molocue Line is an overhead line that will be operated by Electricidade de Mocambique EP. The line will carry alternating current (AC) through single circuit cable. Buy the profile here.

4. Namialo – Metoro Line

The Namialo – Metoro Line is a 400kV overheadNamialo to Metoro. The project is proposed and is expected to be commissioned in 2025.

The Namialo – Metoro Line is an overhead line that will be operated by Electricidade de Mocambique EP. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

5. Vilanculo – Maputo Line

The Vilanculo – Maputo Line is a 400kV overhead line with a length of 563Ckm running from Vilanculo to Maputo. The project is under construction and is expected to be commissioned in 2023.

The Vilanculo – Maputo Line is an overhead line that will be operated by Electricidade de Mocambique EP. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

For more details on the latest transmission line projects, buy the project profiles here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying data, research, and analysis used to produce this article.

GlobalData’s Power Intelligence Center provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide, while its capacity and generation database provides historic and forecast power generation and generation capacity by technology as well as consumption, imports and exports for over 170 countries.