Global transmission line length was estimated to have reached 5,465,957Ckm by the end of 2021 and is forecasted to grow to 6,485,343Ckm by 2027. Norway had 35,454Ckm of line length in 2021 and this is expected to rise to 41,787Ckm by 2027. Listed below are the five largest transmission projects by line length in Norway, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission line segment. Buy the latest transmission line project profiles here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Global transmission line project profiles

Buy the profiles

Premium Insights

The gold standard of business intelligence.

Find out more

1. Aurland – Sogndal Line

The Aurland – Sogndal Line is a 420kV overhead line with a length of 70Ckm running from Aurland to Sogndal. The project is under construction and is expected to be commissioned in 2023.

The Aurland – Sogndal Line is an overhead line that will be operated by Statnett SF. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

2. Balsfjord – Hammerfest Line

The Balsfjord – Hammerfest Line is a 420kV overhead line with a length of 360Ckm running from Balsfjord to Hammerfest(Skaidi). The project is under construction and is expected to be commissioned in 2023.

The Balsfjord – Hammerfest Line is an overhead line that will be operated by Statnett SF. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

3. Klaebu – Viklandet – Aura Line

The Klaebu – Viklandet – Aura Line is a 420kV overhead line with a length of 133Ckm running from Klaebu to Aura. The project is planned and is expected to be commissioned in 2028.

The Klaebu – Viklandet – Aura Line is an overhead line that will be operated by Statnett SF. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

4. Lyse – Stoleheia Line

The Lyse – Stoleheia Line is a 420kV overhead line with a length of 76Ckm running from Lyse to Stoleheia. The project is under construction and is expected to be commissioned in 2023.

The Lyse – Stoleheia Line is an overhead line that will be operated by Statnett SF. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

5. Namsos – Storheia Line

The Namsos – Storheia Line is a 420kV overhead line with a length of 120Ckm running from Namsos to Storheia (Afjord). The project is under construction and is expected to be commissioned in 2028.

The Namsos – Storheia Line is an overhead line that will be operated by Statnett SF. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

For more details on the latest transmission line projects, buy the project profiles here.

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying data, research, and analysis used to produce this article.

GlobalData’s Power Intelligence Center provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide, while its capacity and generation database provides historic and forecast power generation and generation capacity by technology as well as consumption, imports and exports for over 170 countries.