Global transmission line length was estimated to have reached 5,767,158Ckm by the end of 2023 and is forecasted to grow to 6,669,519Ckm by 2028. Russia had 154,488Ckm of line length in 2023 and this is expected to rise to 168,591Ckm by 2028. Listed below are the five largest transmission projects by line length in Russia, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission line segment. Buy the latest transmission line project profiles here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Power Transmission Project Profiles

Buy the Profiles

Data Insights

The gold standard of business intelligence.

Find out more

1. Kalinin – Vladimir Line

The Kalinin – Vladimir Line is a 750kV overheadKalinin to Vladimir. The project is planned and is expected to be commissioned in 2024.

The Kalinin – Vladimir Line is an overhead line that will be operated by Federal Grid Company – Rosseti. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

2. Koporskaya – Leningrad Line

The Koporskaya – Leningrad Line is a 750kV overhead line with a length of 5.1Ckm running from Koporskaya to Leningrad. The project is planned and is expected to be commissioned in 2025.

The Koporskaya – Leningrad Line is an overhead line that will be operated by Federal Grid Company – Rosseti. The line will carry alternating current (AC) through single circuit cable. Buy the profile here.

3. Leningradskaya – Belozerskaya Line

The Leningradskaya – Belozerskaya Line is a 750kV overheadLeningradskaya to Belozerskaya. The project is under construction and is expected to be commissioned in 2024.

The Leningradskaya – Belozerskaya Line is an overhead line that will be operated by Federal Grid Company – Rosseti. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

4. Novosokolniki – Talashkino Line

The Novosokolniki – Talashkino Line is a 750kV overheadNovosokolniki to Talashkino. The project is under construction and is expected to be commissioned in 2024.

The Novosokolniki – Talashkino Line is an overhead line that will be operated by Federal Grid Company – Rosseti. The line will carry alternating current (AC) through double circuit cable. Buy the profile here.

5. Nizhneangarsk – Chara Line

The Nizhneangarsk – Chara Line is a 500kV overheadNizhneangarsk to Chara. The project is under construction and is expected to be commissioned in 2024.

The Nizhneangarsk – Chara Line is an overhead line. through 96540 circuit cable. Buy the profile here.

For more details on the latest transmission line projects, buy the project profiles here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying data, research, and analysis used to produce this article.

GlobalData’s Power Intelligence Center provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide, while its capacity and generation database provides historic and forecast power generation and generation capacity by technology as well as consumption, imports and exports for over 170 countries.