Global transmission capacity was estimated to have reached 21,846,736MVA by the end of 2022 and is forecasted to grow to 28,915,469MVA by 2028. Colombia had 38,094MVA of capacity in 2022 and this is expected to rise to 43,075MVA by 2028. Listed below are the five largest transmission projects by capacity in Colombia, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission segment. Buy the latest transmission substation project profiles here.
1. Bolivar Substation
Bolivar Substation is a 500/220kV substation located at Bolivar, Bolivar, Colombia. The substation is under construction and is expected to be commissioned in 2024. The Bolivar Substation will be operated by Unidad de Planeacion Minero Energetica.
The designed voltage level of the substation is 500/220kV and the operating voltage level is 500/220kV. The step in voltage of the project is 500kV and the step out voltage is 220kV. Upon completion, the substation will be able to operate at 450MVA.
Bolivar Substation is owned by Unidad de Planeacion Minero Energetica. Buy the profile here.
2. Copey Substation
Copey Substation is a 500/220kV substation located at Copey, Cesar, Colombia. The substation is under construction and is expected to be commissioned in 2024. The Copey Substation will be operated by Unidad de Planeacion Minero Energetica.
The designed voltage level of the substation is 500/220kV and the operating voltage level is 500/220kV. The step in voltage of the project is 500kV and the step out voltage is 220kV. Upon completion, the substation will be able to operate at 450MVA.
Copey Substation is owned by Unidad de Planeacion Minero Energetica. Buy the profile here.
3. Medellin Substation
Medellin Substation is a 500/230kV substation located at Medellin, Antioquia, Colombia. The substation is under construction and is expected to be commissioned in 2024. The Medellin Substation will be operated by Unidad de Planeacion Minero Energetica.
The designed voltage level of the substation is 500/230kV and the operating voltage level is 500/230kV. The step in voltage of the project is 500kV and the step out voltage is 230kV. Upon completion, the substation will be able to operate at 900MVA.
Medellin Substation is owned by Unidad de Planeacion Minero Energetica. Buy the profile here.
4. Ocana Substation
Ocana Substation is a 500/230kV substation located at Ocana, Norte de Santander, Colombia. The substation is under construction and is expected to be commissioned in 2024. The Ocana Substation will be operated by Unidad de Planeacion Minero Energetica.
The designed voltage level of the substation is 500/230kV and the operating voltage level is 500/230kV. The step in voltage of the project is 500kV and the step out voltage is 230kV. Upon completion, the substation will be able to operate at 360MVA.
Ocana Substation is owned by Unidad de Planeacion Minero Energetica. Buy the profile here.
5. Sahagun Substation
Sahagun Substation is a 500kV substation located at Sahagun, Córdoba, Colombia. The substation is planned and is expected to be commissioned in 2025. The Sahagun Substation will be operated by Unidad de Planeacion Minero Energetica.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Sahagun Substation is owned by Unidad de Planeacion Minero Energetica. Buy the profile here.
For more details on the latest transmission substation projects, buy the project profiles here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.