Global transmission capacity was estimated to have reached 21,846,736MVA by the end of 2022 and is forecasted to grow to 28,915,469MVA by 2028. Myanmar had 24,584MVA of capacity in 2022 and this is expected to rise to 26,581MVA by 2028. Listed below are the five largest transmission projects by capacity in Myanmar, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission segment. Buy the latest transmission substation project profiles here.
1. Kanbauk Substation
Kanbauk Substation is a 500kV substation located at Kanbauk, Tanintharyi, Myanmar. The substation is planned and is expected to be commissioned in 2025. The Kanbauk Substation will be operated by Ministry of Electricity and Energy, Myanmar.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Kanbauk Substation is owned by Ministry of Electricity and Energy, Myanmar. Buy the profile here.
2. Meik Hti La Substation
Meik Hti La Substation is a 500/230/33kV substation located at Meik Hti La, Mandalay, Myanmar. The substation is under construction and is expected to be commissioned in 2024. The Meik Hti La Substation will be operated by Ministry of Electricity and Energy, Myanmar.
The designed voltage level of the substation is 500/230/33kV and the operating voltage level is 500/230/33kV. The step in voltage of the project is 500kV and the step out voltage is 33kV. Upon completion, the substation will be able to operate at 1500MVA.
Meik Hti La Substation is owned by Ministry of Electricity and Energy, Myanmar. Buy the profile here.
3. Myeiktilar Substation
Myeiktilar Substation is a 500kV substation located at Myeiktilar, Bago, Myanmar. The substation is under construction and is expected to be commissioned in 2024. The Myeiktilar Substation will be operated by Ministry of Electricity and Energy, Myanmar.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Myeiktilar Substation is owned by Ministry of Electricity and Energy, Myanmar. Buy the profile here.
4. Phayagyi Substation
Phayagyi Substation is a 500kV substation located at Phayagyi, Pagoda, Myanmar. The substation is under construction and is expected to be commissioned in 2024. The Phayagyi Substation will be operated by Ministry of Electricity and Energy, Myanmar.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Phayagyi Substation is owned by Ministry of Electricity and Energy, Myanmar. Buy the profile here.
5. Taungoo Substation – New – 500 kV
Taungoo Substation – New – 500 kV is a 500kV substation located at Taungoo, Bago, Myanmar. The substation is under construction and is expected to be commissioned in 2024. The Taungoo Substation – New – 500 kV will be operated by Ministry of Electricity and Energy, Myanmar.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Taungoo Substation – New – 500 kV is owned by Ministry of Electricity and Energy, Myanmar. Buy the profile here.
For more details on the latest transmission substation projects, buy the project profiles here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.