Adani Khirsara Solar PV Park – 2 is a 100MW solar PV power project. It is located in Gujarat, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in December 2020.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 100 | 100 | – | Active | Gujarat, India | Adani Solar Energy Kutchh Two |
---|
Description
The project is developed and owned by Adani Solar Energy Kutchh Two. The company has a stake of 100%.
Adani Khirsara Solar PV Park – 2 is a ground-mounted solar project.
The project cost is $72.5m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in December 2020.
Power Purchase Agreement
The power generated from the project is sold to Gujarat Urja Vikas Nigam under a power purchase agreement. The power is sold at the rate of $0.033kWh for a period of 25 years, starting from 2021. The contracted capacity is 100MW.
About Adani Solar Energy Kutchh Two
Adani Solar Energy Kutchh Two Pvt Ltd (ASEKT) operates and maintains hybrid power projects, utility-scale grid connected solar power plants, wind plants and solar parks. ASEKT is headquartered in Khirsara, Gujarat, India.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.