Arkun is a 245MW hydro power project. It is located on Coruh river/basin in Erzurum, Turkey. The project is currently active. It has been developed in single phase. The project construction commenced in 2010 and subsequently entered into commercial operation in 2014.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 245 | 245 | – | Active | Erzurum, Turkey | Enerjisa Enerji Uretim |
---|
Description
The project is developed and owned by Enerjisa Enerji Uretim.
Arkun is a reservoir based project. The net head of the project is 192m. The project generated 800 GWh of electricity. The project cost is $703.15m.
Development Status
The project construction commenced in 2010 and subsequently entered into commercial operation in 2014.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
The turbines for the hydro power project have been supplied by GE Renewable Energy and Kossler.
The electric generators for the project were procured from GE Renewable Energy and Voith Hydro Holding.
About Enerjisa Enerji Uretim
Enerjisa Enerji Uretim AS (Enerjisa Enerji), is an energy utility company. The company generates electricity from lignite coal, hydro, natural gas and wind sources. It owns and operates wind plants such as Canakkale in Mahmudiye, Dagpazari in Mut, and Balikesir in Balikesir province; Tufanbeyli lignite power plant in Tufanbeyli; hydroelectric power plants such as Dagdelen, Kusakli, Cambasi, Yamanli II, Menge, Sariguzel, Hacininoglu, Kopru, Kavsak bendi, Kandil, Arkun among others; and natural gas plants such as Kentsa, Bandirma II, and Bandirma I in Bandirma and Kocaeli. The company invests in the development of various power projects in the country. Enerjisa Enerji is headquartered in Istanbul, Turkey.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.