The Ashburn Data Center Project is a smart grid project being developed in Ashburn, Virginia, US. It is an advanced grid infrastructure project.
The project is expected to be completed in 2021.
Description
The Ashburn Data Center Project is currently under construction and will use smart grid technology. The project has a rated capacity of 180MW.
The smart grid project is being installed by Aligned Energy.
The Ashburn Data Center Project has the following equipment associated with it:
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalData- – Data Center
Ashburn Data Center Project development status
The project is expected to be commissioned in 2021.
Contractors involved
Aligned Energy will construct and complete the Ashburn Data Center Project.
Additional information
– Aligned Energy, a leading data center provider offering innovative, sustainable and adaptable colocation and build-to-scale solutions for cloud, enterprise, and managed service providers, announces the completion of phase one of its hyperscale data center campus in Ashburn, Virginia.
– The initial 368,755 square-foot, 60 MW facility will be followed by a 409,000 square-foot, 120 MW development on the 26-acre campus.
– At full build, the planned Aligned Ashburn campus will offer over 1 MM square feet of space and 180 MW of total critical load in the heart of Loudoun County, Virginia — the nation’s most robust data center market.
About Aligned Energy
Aligned Energy LLC (Aligned Energy) is an infrastructure technology company. It provides consumption based colocation, electrical and mechanical infrastructure and data center services. Aligned Energy is headquartered in Plano, Texas, the US.
Methodology
All publicly-announced smart grid projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific power players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.