Banha Combined Cycle Project is a 750MW gas fired power project. It is located in Qalyubia, Egypt. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in May 2015.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 750 750 Active Qalyubia, Egypt

Description

The project is currently owned by Middle Delta Electricity Production.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $500m.

Development Status

The project got commissioned in May 2015.

Contractors Involved

SEPCOIII Electric Power Construction was selected to render EPC services for the gas fired power project.

The Gas fired project have been supplied by Ansaldo Energia and GE Power.

Ansaldo Energia supplied electric generator for the project.

AC Boilers supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.