Belozerskaya Substation – Upgrade – 500 kV, Russia

By Carmen

Belozerskaya Substation – Upgrade – 500 kV is a 500kV substation located in Belozerskaya, Krasnodarskiy, Russia.

The works are expected to be commissioned in 2021.

Description

Belozerskaya Substation – Upgrade – 500 kV project, which is an upgrade substation, will be operated by Federal Grid Company of Unified Energy System.

The designed voltage level of the substation is 500kV and the operating voltage level is 500kV.

The step-in voltage of the project is 500kV. Upon completion, the substation will have a capacity of 1503MVA.

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

Belozerskaya Substation – Upgrade – 500 kV project development status

The project is expected to be commissioned in 2021. Approximately $113.08m was financed by the authorities to undertake the construction works of the project.

About Federal Grid Company of Unified Energy System

Federal Grid Company of Unified Energy System (FGC UES), is a subsidiary of Rosseti, is an energy company which operates and manages unified national electricity transmission grid system. The company transmits electricity to distribution grid companies, large commercial end customers and retail electricity supply companies; and provides connection services. FGC UES also sells electricity produced by its group company, JSC Mobile GTPP and provides construction services for electric grid facilities. It carries out property lease, maintenance and repair of electric grids, communication services, and design and survey. FGC UES is headquartered in Moscow, Russia.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU