Camden Power Station is a 1,561MW coal fired power project. It is located in Mpumalanga, South Africa. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,561 | 1,561 | – | Active | Mpumalanga, South Africa |
---|
Description
The project is currently owned by Eskom Holdings SOC with a stake of 100%.
It is a steam turbine power plant. The fuel is procured from Usutu South, West and East Mines – Trans-Natal Coal Mining Company.
Development Status
The project got commissioned in March 2005.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
Camden Power Station (Camden Power Station Unit I) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.
Camden Power Station (Camden Power Station Unit II) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.
Camden Power Station (Camden Power Station Unit III) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.
Camden Power Station (Camden Power Station Unit IV) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 196MW nameplate capacity.
Camden Power Station (Camden Power Station Unit V) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 195MW nameplate capacity.
Camden Power Station (Camden Power Station Unit VI) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 195MW nameplate capacity.
Camden Power Station (Camden Power Station Unit VII) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 190MW nameplate capacity.
Camden Power Station (Camden Power Station Unit VIII) is equipped with Siemens Double Cylider Reaction Type steam turbine. The phase consists of 1 steam turbine with 185MW nameplate capacity.
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit I).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit II).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit III).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit IV).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit V).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VI).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VII).
Siemens supplied Hydrogen Cooled electric generator for the Camden Power Station (Camden Power Station Unit VIII).
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit I). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit II). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit III). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit IV). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit V). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VI). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VII). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Actom supplied steam boiler for the Camden Power Station (Camden Power Station Unit VIII). The fuel consumption rate inside the boiler is 13.608Tonnes per hour.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.