Castelnou Combined Cycle Power Plant is a 760MW gas fired power project. It is located in Aragon, Spain. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 2006.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 760 760 Active Aragon, Spain

Description

The project is currently owned by Engie with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Reserve.

The project cost is $718.109m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project got commissioned in July 2006.

Contractors Involved

Initec Energia was selected to render EPC services for the gas fired power project.

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 280MW nameplate capacity.

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of M701F gas turbines, each with 240MW nameplate capacity.

Mitsubishi Power supplied Hydrogen Cooled electric generator for the project.

John Cockerill Group supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.