Cheong pyeong is a 139.6MW hydro power project. It is located on Han river/basin in Gyeonggi, South Korea. The project is currently active. It has been developed in multiple phases. The project construction commenced in 1939 and subsequently entered into commercial operation in 1943.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 139.6 139.6 Active Gyeonggi, South Korea

Description

The project is currently owned by Korea Hydro & Nuclear Power.

The hydro reservoir capacity is 185.5 million cubic meter. The project generated 276.1 GWh of electricity.

Development Status

The project construction commenced in 1939 and subsequently entered into commercial operation in 1943.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Cheong pyeong (Cheong pyeong I) is equipped with Hitachi Mitsubishi Hydro propeller turbine. The phase consists of 1 turbine with 40MW nameplate capacity.

Cheong pyeong (cheong pyeong II) is equipped with Hitachi Mitsubishi Hydro kaplan turbines. The phase consists of 2 turbines with 19.8MW nameplate capacity.

Cheong pyeong (Cheong pyeong III) is equipped with Voith Hydro Holding kaplan turbine. The phase consists of 1 turbine with 60MW nameplate capacity.

Hitachi Mitsubishi Hydro supplied electric generator(s) for the Cheong pyeong (Cheong pyeong I). The generator capacity is 43 MVA.

Hitachi Mitsubishi Hydro supplied electric generator(s) for the Cheong pyeong (cheong pyeong II). The generator capacity is 22 MVA.

Voith Hydro Holding supplied electric generator(s) for the Cheong pyeong (Cheong pyeong III). The generator capacity is 70.9 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.