Ciudad Rodrigo – Almaraz C.N. Line is a 400kV overhead line with a length of 132km from Ciudad Rodrigo, Castilla y Leon, Spain, to Almaraz C.N., Extremadura, Spain.

The project, which is currently in the planning stage, is expected to be commissioned in 2021.

Description

Ciudad Rodrigo – Almaraz C.N. Line is an overhead line that will be operated by Red Electrica Corporacion. The line will carry alternating current (AC) through single circuit cable.

Ciudad Rodrigo – Almaraz C.N. Line project development status

The construction works on the Ciudad Rodrigo – Almaraz C.N. Line project commissioning is expected in 2021.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

About Red Electrica Corporacion

Red Electrica Corporacion SA (REC) carries out transmission, generation, distribution and operation of the transmission network for the Spanish electricity system. The company operates the regulated activities through its principal subsidiary, Red Electrica de Espana, S.A. (REE), a transmission system operator and other subsidiaries. REC is involved in electricity transmission activities outside Spain and provides telecommunications services. The company also undertakes the construction of international interconnections, energy storage and financing and risk reinsurance. It serves the third parties in Spain, Peru, Chile and among others. REC is headquartered in Alcobendas, Madrid, Spain.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.