El Burgo de Ebro Biomass Power Plant is a 50MW biopower project. It is located in Aragon, Spain. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2011.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Biopower 50 50 Active Aragon, Spain

Description

The project cost is $188.909m.

Sewage sludge which is a kind of municipal solid waste is used as a feedstock to power the project.

Development Status

The project got commissioned in 2011.

Contractors Involved

Siemens was selected as the steam turbine supplier for the project.

Metso Power supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.