Generation equipment contracts in April 2021 saw 42 contracts announced, marking a drop of 61% over the last 12-month average of 108, according to GlobalData’s power industry contracts database.
- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
The proportion of contracts by category tracked by GlobalData in the month was as follows:
- Supply & Erection: 40 contracts and a 95.2% share
- Project Implementation: one contract and a 2.4% share
- Repair, Maintenance, Upgrade & Others: one contract and a 2.4% share.
Asia-Pacific leads generation equipment activity in April 2021
Comparing contracts activity in generation equipment segment in different regions of the globe, Asia-Pacific held the top position with 16 contracts and a share of 38.1% during April 2021, followed by Europe with 16 contracts and a 38.1% share and Middle East and Africa with four contracts and a 9.5% share.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalData- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
Solar is leading technology for generation equipment contracts in April 2021
Among the technologies, solar accounted for 15 contracts with a 36.6% share, followed by wind with 14 contracts and a 34.1% share and thermal with six contracts and a 14.6% share.
Generation equipment contracts in April 2021: Top issuers by capacity
The top issuer of generation equipment contracts for the month in terms of power capacity involved was:Concord Pacific Developments (Canada) with 106MW from one contract.
Generation equipment contracts in April 2021: Top winners by capacity
The top winner of contracts for the month in terms of power capacity involved was:Gp Joule Canada (Canada) with 106MW from one contract.
All publicly-announced contracts are included in this analysis drawn from GlobalData’s Power database, which covers power plants, T&D projects, equipment markets, analysis reports, capacity and generation, and tracks tenders and contracts on a real-time basis.
More in-depth reports and analysis on all reported contracts are available for subscribers to GlobalData’s Power database.