Gresik Combined Cycle Power Plant is a 1,578.78MW gas fired power project. It is located in East Java, Indonesia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1992.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,578.78 | 1,578.78 | – | Active | East Java, Indonesia |
---|
Description
The project is currently owned by PT Pembangkitan Jawa-Bali with a stake of 100%.
It is a combined cycle gas turbine (ccgt) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on High Speed Diesel. The fuel is procured from PT. Pertamina Hulu Energi WMO.
Development Status
The project got commissioned in 1992.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
Mitsubishi Power was selected to render EPC services for the gas fired power project.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block I) is equipped with Mitsubishi Power M701D gas turbines. The phase consists of 3 gas turbines with 112.45MW nameplate capacity.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block I) is equipped with Mitsubishi Power TC2F-33.5 steam turbine. The phase consists of 1 steam turbine with 188.91MW nameplate capacity.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block II – GT) is equipped with Mitsubishi Power M701D gas turbines. The phase consists of 3 gas turbines with 112.45MW nameplate capacity.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block II – ST) is equipped with Mitsubishi Power TC2F-33.5 steam turbine. The phase consists of 1 steam turbine with 188.91MW nameplate capacity.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block III) is equipped with Mitsubishi Power M701D gas turbines. The phase consists of 3 gas turbines with 112.45MW nameplate capacity.
Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block III) is equipped with Mitsubishi Power TC2F-33.5 steam turbine. The phase consists of 1 steam turbine with 188.91MW nameplate capacity.
Siemens supplied electric generator for the Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block I).
Siemens supplied electric generator for the Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block II – GT).
Siemens supplied electric generator for the Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block II – ST).
Siemens supplied electric generator for the Gresik Combined Cycle Power Plant (Gresik Combined Cycle Power Plant Block III).
John Cockerill Group supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.