Harts Mill Solar PV Park is an 112MW solar PV power project. It is located in North Carolina, the US. The project is currently active. It has been developed in single phase. The project construction commenced in 2020 and subsequently entered into commercial operation in January 2021.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 112 112 Active North Carolina, the US Birch Creek Development; Harts Mill Solar; Pine Gate Renewables; SunEnergy1

Description

The project was developed by Birch Creek Development, Harts Mill Solar, Pine Gate Renewables and SunEnergy1. The project is currently owned by Kayne Anderson Capital Advisors.

Harts Mill Solar PV Park is a ground-mounted solar project.

The project generates 193,957.198MWh of electricity. The project cost is $120.736m.

The project consists of 367,213 modules, each with 350W nameplate capacity.

54 inverters have been installed at the project site.

Development Status

The project construction commenced in 2020 and subsequently entered into commercial operation in January 2021.

Contractors Involved

Pine Gate Renewables was selected to render EPC services for the solar PV power project.

About Birch Creek Development

Birch Creek Development LLC (Birch Creek) is a financial service provider company. Birch Creek is headquartered in El Segundo, the US.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.