Hennigsdorf Substation is a 380kV substation located in Hennigsdorf, Brandenburg, Germany.

The Hennigsdorf Substation project’s construction is expected to begin in 2023. The works are expected to be commissioned in 2024.

Description

Hennigsdorf Substation project, which is an upgrade substation, will be operated by 50Hertz Transmission.

The designed voltage level of the substation is 380/220kV and the operating voltage level is 380/220kV.

The step-in voltage of the project is 380kV and the step-out voltage is 220kV. Upon completion, the substation will have a capacity of 400MVA.

Hennigsdorf Substation project development status

The project is expected to be commissioned in 2024.

About 50Hertz Transmission

50Hertz Transmission GmbH (50Hertz), is a subsidiary of Eurogrid GMBH, is a power company that provides power and electricity transmission services. The company’s services include operation, planning, maintenance, and expansion of transmission grid across the northern and eastern Germany. Its grid operates through stations from Berlin to Rio de Janeiro. 50Hertz operates its power transmission projects across Germany. The company operates through its substations, power stations, and switch station. It has its operations in Germany, Poland, Denmark, the Czech Republic, and Scandinavia. 50Hertz is headquartered in Berlin, Germany.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.