Hirono Coal Fired Power Plant is a 1,200MW coal fired power project. It is located in Fukushima, Japan. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2004.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,200 1,200 Active Fukushima, Japan

Description

The project is currently owned by JERA with a stake of 100%.

It is a steam turbine power plant.

Development Status

The project got commissioned in July 2004.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Mitsubishi Power was selected as the turbine supplier for thermal power project. The project consists of 2 units of Tandem Compound, Double Exhaust, Reheat Condensing Type turbines, each with 600MW nameplate capacity.

Mitsubishi Power supplied Three-Phase AC Synchronous electric generator for the Hirono Coal Fired Power Plant (Hirono Coal Fired Power Plant Unit I).

Mitsubishi Power supplied steam boiler for the Hirono Coal Fired Power Plant (Hirono Coal Fired Power Plant Unit I).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.