The Huadian Shunde Western Energy Station Phase II Project is 500MW gas fired power project. It is planned in Guangdong, China. The project is currently in permitting stage. It will be developed in single phase. Post completion of the construction, the project is expected to get commissioned in 2023.

Project TypeTotal Capacity (MW)Active Capacity (MW)Pipeline Capacity (MW)Project StatusProject LocationProject DeveloperThermal500-500PermittingGuangdong, ChinaHuadian Foshan Energy

Description

The project is being developed and currently owned by Huadian Foshan Energy.

It is a ccgt with cogen power plant.

The project cost is expected to be around $237.89m.

Development Status

Post completion of the construction, the project is expected to get commissioned in 2023.

About Huadian Foshan Energy

Huadian Foshan Energy Co Ltd (Huadian Foshan Energy) generates electric power. The company is headquartered in China.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.