Ilsan Combined Heat & Power Plant is a 900MW gas fired power project. It is located in Gyeonggi, South Korea. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1993.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 900 | 900 | – | Active | Gyeonggi, South Korea |
---|
Description
The project is currently owned by Korea East-West Power.
It is a CCGT with Cogen power plant.
The project generated 3,916,000MWh of electricity.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in December 1993.
Contractors Involved
GS E&C was selected to render EPC services for the gas fired power project.
Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase I) is equipped with Siemens steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.
Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase I) is equipped with Siemens SGT6-3000E gas turbines. The phase consists of 4 gas turbines with 100MW nameplate capacity.
Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase II) is equipped with Siemens steam turbine. The phase consists of 1 steam turbine with 100MW nameplate capacity.
Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase II) is equipped with Siemens SGT6-3000E gas turbines. The phase consists of 2 gas turbines with 100MW nameplate capacity.
BRUSH Turbogenerators supplied electric generator for the Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase I).
Mitsubishi Heavy Industries supplied electric generator for the Ilsan Combined Heat & Power Plant (Ilsan Combined Heat & Power Plant Phase II).
Mitsubishi Heavy Industries supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.