Jiangsu Changshu Power Plant is a 1,950MW coal fired power project. It is located in Jiangsu, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2005.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,950 1,950 Active Jiangsu, China

Description

The project is currently owned by China Resources Power Holdings with a stake of 100%.

It is a steam turbine power plant.

Development Status

The project got commissioned in March 2005.

Contractors Involved

Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit I) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 650MW nameplate capacity.

Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit II) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 650MW nameplate capacity.

Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit III) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 650MW nameplate capacity.

DEC Dongfang Electric Machinery supplied QFSN-600-2-22A electric generator for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit I).

DEC Dongfang Electric Machinery supplied QFSN-600-2-22A electric generator for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit II).

DEC Dongfang Electric Machinery supplied QFSN-600-2-22A electric generator for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit III).

Doosan Heavy Industries & Construction supplied steam boiler for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit I).

Doosan Heavy Industries & Construction supplied steam boiler for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit II).

Doosan Heavy Industries & Construction supplied steam boiler for the Jiangsu Changshu Power Plant (Jiangsu Changshu Power Plant Unit III).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.