Kaliakra Wind Power AD is a 35MW onshore wind power project. It is located in Dobrich, Bulgaria. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 2008.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 35 35 Active Dobrich, Bulgaria Kaliakra Wind Power

Description

The project was developed by Kaliakra Wind Power. Mitsubishi Heavy Industries and INOS-1 are currently owning the project having ownership stake of 70% and 30% respectively.

The electricitiy generated from the plant has offsetted 70,000t of carbon dioxide emissions (CO2) a year. The project cost is $84.525m.

Development Status

The project is currently active. The project got commissioned in July 2008.

Power Purchase Agreement

The power generated from the project is sold to Natsionalna Elektricheska Kompania under a power purchase agreement for a period of 12 years.

Contractors Involved

INOS-1 and Mitsubishi Heavy Industries were selected to render EPC services for the wind power project.

Mitsubishi Heavy Industries was selected as the turbine supplier for the wind power project. The company provided 35 units of MWT-1000A/1.0 turbines, each with 1MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.