Karabatan Power Plant is a 312MW gas fired power project. It is located in Atyrau, Kazakhstan. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in April 2020.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 312 | 312 | – | Active | Atyrau, Kazakhstan | Karabatan Utility Solutions |
---|
Description
The project is developed and owned by Karabatan Utility Solutions.
It is a CCGT with Cogen power plant. The fuel is procured from Tengiz field.
The project cost is $320.78m.
Development Status
The project got commissioned in April 2020.
Contractors Involved
Doosan Heavy Industries & Construction was selected to render EPC services for the gas fired power project.
The Gas fired project have been supplied by Doosan Skoda Power and Siemens.
Doosan Skoda Power supplied electric generator for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.