Karbala Oil Fired Power Plant is a 288MW oil fired power project. It is located in Karbala, Iraq. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 2012.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 288 288 Active Karbala, Iraq

Description

The project is currently owned by Ministry of Electricity, Iraq with a stake of 100%.

It is a Internal Combustion power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is heavy fuel oil. In case of shortage of heavy fuel oil the plant can also run on Distillate Fuel oil.

The project cost is $228.658m.

Development Status

The project got commissioned in July 2012.

Contractors Involved

STX was selected to render EPC services for the oil fired power project.

MAN Energy Solutions was selected as the engine supplier for the Oil fired project. The company provided 72 units of 18V28/32S engines, each with 4MW nameplate capacity.

STX is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2012, for a period of one year.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.