Kot Addu Power Plant is a 1,600MW gas fired power project. It is located in Punjab, Pakistan. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1987.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,600 1,600 Active Punjab, Pakistan

Description

The project is currently owned by Kot Addu Power with a stake of 100%.

It is a combined cycle gas turbine (ccgt) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on High Speed Diesel. The fuel is procured from Sui Northern Gas Pipelines Ltd, Pakistan State Oil.

Development Status

The project got commissioned in 1987.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Power Purchase Agreement

The power generated from the project is sold to Pakistan Water and Power Development Authority under a power purchase agreement for a period of 0 years.

Contractors Involved

Ansaldo Energia, Descon Engineering, Siemens and Tractebel Engineering were selected to render EPC services for the gas fired power project.

The Gas fired project have been supplied by GE Power and Siemens.

The electric generators for the project were procured from GE Power and Siemens.

CMI Solar and Electric supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.