Lakadia – Vadodara Line is a 765kV overhead line with a length of 330km from Lakadia, Gujarat, India, to Vadodara, Gujarat, India.

The project, which is currently under construction, is expected to be commissioned in 2022.

Description

Lakadia – Vadodara Line is an overhead line that will be operated by Sterlite Grid. The line will carry alternating current (AC) through double circuit cable.

Approximately $278.66m was financed by the authorities to undertake the construction works of the project.

The development of the Lakadia – Vadodara Line project has been approved by the Gujarat Electricity Regulatory Commission.

Lakadia – Vadodara Line project development status

The construction works on the Lakadia – Vadodara Line project were commenced in 2019 and commissioning is expected in 2022.

Contractors involved

Associated Power Structures Pvt and Tata Projects was appointed by Sterlite Grid to undertake the construction works on the Lakadia – Vadodara Line project.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.