Mellach Combined Cycle Power Plant is an 832MW gas fired power project. It is located in Styria, Austria. The project is currently active. It has been developed in single phase. The project construction commenced in 2009 and subsequently entered into commercial operation in June 2012.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 832 832 Active Styria, Austria Siemens

Description

The project was developed by Siemens and is currently owned by Verbund Thermal Power with a stake of 100%.

It is a CCGT with Cogen power plant.

The project generated 915,000MWh of electricity. The project cost is $696.306m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project construction commenced in 2009 and subsequently entered into commercial operation in June 2012.

Contractors Involved

Siemens was selected to render EPC services for the gas fired power project.

Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT5-4000F gas turbines.

Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SST5-5000 steam turbines.

Siemens supplied Two-Pole, Hydrogen-Cooled, SGen5-2000H electric generator for the project.

Siemens supplied steam boiler for the project.

About Siemens

Siemens AG (Siemens) is a technology company. Its operations span electrification, automation and digitalization fields. The company designs, develop and manufactures products, and installs complex systems and projects. It also provides a wide range of customized solutions for individual requirements. Siemens focuses on power generation and distribution, and intelligent infrastructure for buildings and distributed energy systems. It provides smart mobility solutions for rail and road transport, medical technology, and digital healthcare services. Siemens has research and development facilities, production plants, warehouses, and sales offices across the world. It serves customers in various industries such as energy, healthcare, infrastructure, process and manufacturing, and others. Siemens is headquartered in Munich, Bavaria, Germany.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.