Mosenergo TEP-22 Power Plant is a 1,070MW gas fired power project. It is located in Moscow, Russia. The project is currently active. It has been developed in single phase. The project construction commenced in 1956 and subsequently entered into commercial operation in December 1960.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,070 | 1,070 | – | Active | Moscow, Russia |
---|
Description
The project is currently owned by Mosenergo with a stake of 100%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Coal.
The project generated 8,107,000MWh of electricity.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project construction commenced in 1956 and subsequently entered into commercial operation in December 1960.
Contractors Involved
The Gas fired project have been supplied by Leningradsky Metallichesky Zavod and Ural Turbine Works.
The electric generators for the project were procured from Electrosila and NPO Elsib.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.