Moss Landing Steam Turbine Energy Facility is a 1,404MW gas fired power project. It is located in California, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1967.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,404 | 1,404 | – | Active | California, the US |
---|
Description
The project is currently owned by Dynegy Moss Landing with a stake of 100%.
It is a steam turbine power plant that is used for Peakload. The fuel is procured from Pacific Gas & Electric.
The project generated 79,224MWh of electricity.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in December 1967.
Contractors Involved
GE Power was selected as the turbine supplier for thermal power project. The project consists of 2 units of Cross Compound turbines, each with 702MW nameplate capacity.
GE Power supplied electric generator for the Moss Landing Steam Turbine Energy Facility (Moss Landing Steam Turbine Energy Facility Unit I).
GE Power supplied electric generator for the Moss Landing Steam Turbine Energy Facility (Moss Landing Steam Turbine Energy Facility Unit II).
Babcock & Wilcox Enterprises supplied steam boiler for the Moss Landing Steam Turbine Energy Facility (Moss Landing Steam Turbine Energy Facility Unit I).
Babcock & Wilcox Enterprises supplied steam boiler for the Moss Landing Steam Turbine Energy Facility (Moss Landing Steam Turbine Energy Facility Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.