Muara Tawar Combined Cycle Power Plant Block I & V is a 1,024MW gas fired power project. It is located in West Java, Indonesia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1997.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,024 1,024 Active West Java, Indonesia

Description

The project is currently owned by PT Pembangkitan Jawa-Bali.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Oil. The fuel is procured from PT Nusantara Regas, Perusahaan Gas Negara (PGN), PT Pertamina EP, JOB Pertamina-Talisman Jambi Merang.

Development Status

The project got commissioned in 1997.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Contractors Involved

GE Power was selected to render EPC services for the gas fired power project.

Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block I) is equipped with GE Power DKZ2-2N41 steam turbine. The phase consists of 1 steam turbine with 220MW nameplate capacity.

Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block I) is equipped with GE Power GT13E2 gas turbines. The phase consists of 3 gas turbines with 140MW nameplate capacity.

Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block V) is equipped with GE Power COMAX steam turbine. The phase consists of 1 steam turbine with 234MW nameplate capacity.

Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block V) is equipped with GE Power GT13E2 gas turbine. The phase consists of 1 gas turbine with 150MW nameplate capacity.

GE Power supplied electric generator for the Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block I).

GE Power supplied electric generator for the Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block V).

GE Power supplied steam boiler for the Muara Tawar Combined Cycle Power Plant Block I & V (Muara Tawar Combined Cycle Power Plant Block V).

GE Power and PT Pembangkitan Jawa-Bali were contracted to render operations & maintenance services for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.