South and Central America power industry tenders activity in Q3 2021 saw 93 tenders announced, marking a rise of 12% over the last four-quarter average of 83, according to GlobalData’s power database.

  • Embed this chart

    Embed this chart into your website

    Copy and paste the code below into your website to display the chart.

South and Central America power industry tenders in Q3 2021: Bolivia leads activity

Looking at tenders by country, Bolivia led the activity in Q3 2021 with 42 tenders and a share of 45.2%, up 5.2% over the previous quarter and up 35% when compared with the last four-quarter average, followed by Uruguay with 17 tenders and a share of 18.3% and Paraguay with eight tenders and a share of 8.6% during the quarter.

Looking at the last four-quarter average, Bolivia held the top spot with 31 tenders, followed by Trinidad and Tobago with ten and Uruguay with ten tenders.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

  • Embed this chart

    Embed this chart into your website

    Copy and paste the code below into your website to display the chart.

Solar is top technology area for tenders in Q3 2021

Looking at tenders divided by the type of technology, solar accounted for the largest proportion with 14 tenders and a 45.2% share, followed by hydro with five tenders and a 16.1% share and wind with five tenders and a 16.1% share.

Looking at power industry tenders divided by segment as tracked by GlobalData, T&D Equipment was the most popular segment in South and Central America power tenders activity during Q3 2021, with 42 tenders, followed by T&D Project (25) and Power Plant (13).

The proportion of tenders by category tracked by GlobalData in the quarter was as follows:

  1. Supply & Erection: 50 tenders and a 53.8% share
  2. Project Implementation: 30 tenders and a 32.3% share
  3. Consulting & Similar Services: six tenders and a 6.5% share
  4. Power Purchase Agreement: four tenders and a 4.3% share
  5. Repair, Maintenance, Upgrade & Others: two tenders and a 2.2% share
  6. Electricity Supply: one tender and a 1.1% share.

Power tenders in Q3 2021: Top companies by capacity

The top issuers of tenders for the quarter in terms of power capacity involved in South and Central America were:

  1. Corporacion Electrica del Ecuador (Ecuador) and Ministerio de Energia y Recursos Naturales No Renovables: 500MW from one tender
  2. Guyana Power & Light (Guyana): 33MW from one tender
  3. Banco Centroamericano de Integracion Economica (Honduras): 18.23MW capacity from one tender.

All publicly-announced tenders are included in this analysis drawn from GlobalData’s Power database, which covers power plants, T&D projects, equipment markets, analysis reports, capacity and generation, and tracks tenders and contracts on a real-time basis.