5 de Noviembre is an 182MW hydro power project. It is located on Lempa river/basin in Chalatenango, El Salvador. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1954. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights 5 de Noviembre

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project is developed and owned by Comision Ejecutiva Hidroelectrica del Rio Lempa. The company has a stake of 100%.

5 de Noviembre is a reservoir based project.

The 5 de Noviembre (5 de Noviembre Expansion) has 2 electric generators installed at the site.

Development status

The project got commissioned in 1954.

Contractors involved

5 de Noviembre (5 de Noviembre Expansion) is equipped with Andritz Hydro francis turbines. The phase consists of 2 turbines with 41MW nameplate capacity.

5 de Noviembre (5 de Noviembre I) is equipped with Andritz Hydro francis turbines. The phase consists of 4 turbines with 14.7MW nameplate capacity.

5 de Noviembre (5 de Noviembre I) is equipped with Andritz Hydro francis turbine. The phase consists of 1 turbine with 23.4MW nameplate capacity.

5 de Noviembre (5 de Noviembre I) is equipped with Hitachi Mitsubishi Hydro francis turbine. The phase consists of 1 turbine.

ABB Asea Brown Boveri supplied 4 electric generators for the 5 de Noviembre (5 de Noviembre I).

Hitachi Mitsubishi Hydro supplied electric generator(s) for the 5 de Noviembre (5 de Noviembre I).

For more details on 5 de Noviembre, buy the profile here.

About Comision Ejecutiva Hidroelectrica del Rio Lempa

Comision Ejecutiva Hidroelectrica del Rio Lempa (CEL) is an energy company that offers hydroelectric and solar power generation solutions. The company generates electricity from hydro, solar, biogas, sea waves and wind energy sources. Its activities include photovoltaic research, wind research, electrical generation with biogas, electrical generation with sea waves, and others. CEL’s projects comprises El Chaparral hydroelectric project, Binational hydroelectric project, Photovoltaic Research project, Hydroelectric Guajoyo project and Large Hydroelectric Cerron project, among others. The company operates in La Paz, Santa Ana, Chalatenango, Cabanas, Usulutan and San Miguel. CEL is headquartered in San Salvador, El Salvador.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.