Altamira Combined Cycle Cogeneration Power Plant is a 414MW gas fired power project. It is located in Tamaulipas, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in September 2019. Buy the profile here.
Description
The project is currently owned by ContourGlobal.
It is a CCGT with Cogen power plant.
The project generated 2,900,000MWh of electricity.
Development status
The project got commissioned in September 2019.
Contractors involved
Cobra Energia and Inelectra International were selected to render engineering procurement construction services for the gas fired power project.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SGT6-8000H gas turbine.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SST-800 steam turbine.
Siemens supplied SGen6-2000H electric generator for the project.
Siemens supplied SGen6-2000H electric generator for the project.
Siemens supplied SGen6-100A electric generator for the project.
Siemens supplied SGen6-100A electric generator for the project.
For more details on Altamira Combined Cycle Cogeneration Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.