Altinkaya is a 700MW hydro power project. It is located on Kizilirmak river/basin in Samsun, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1980 and subsequently entered into commercial operation in 1989. Buy the profile here.
Description
The project was developed by YUKSEL CONSTRUCTION and is currently owned by Devlet su Isleri Genel Mudurlugu.
The hydro reservoir capacity is 5,763 million cubic meter. The project generated 1,632 GWh of electricity.
Development status
The project construction commenced in 1980 and subsequently entered into commercial operation in 1989.
Contractors involved
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 4 turbines, each with 175MW nameplate capacity.
Hitachi Mitsubishi Hydro supplied 4 electric generators for the project.
For more details on Altinkaya, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.