The Anwara Combined Cycle Power Plant is 590MW gas fired power project. It is planned in Chittagong, Bangladesh. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in January 2026. Buy the profile here.
Description
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel will be procured from Karnaphuli Gas Distribution Company Limited.
The Gas fired project consists of 1 gas turbine.
The Gas fired project consists of 1 steam turbine.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by January 2026.
Contractors involved
China Energy Engineering Group, China Energy Engineering Group Northwest Construction and Investment and Jalalabad Electric Power are expected to render engineering procurement construction services for the gas fired power project.
See Also:
For more details on Anwara Combined Cycle Power Plant, buy the profile here.
Premium Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.