Anzanan Factory is a 26.3MW biopower project. It is located in Hiroshima, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2013. Buy the profile here.

Description

The project cost is $113.972m.

Refuse which is a kind of municipal solid waste is used as a feedstock to power the project.

Development status

The project got commissioned in March 2013.

Contractors involved

JFE Engineering supplied steam boiler for the project. The boiler installed at the site has a capacity of 36TPH. The temperature witnessed inside the boiler is around 400°C. The steam is pressurized inside the boiler at 52bar.

For more details on Anzanan Factory, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.