The APEX Bethel Gas Fired Power Plant is 476MW gas fired power project. It is planned in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. The project construction is likely to commence in 2024 and is expected to enter into commercial operation in September 2025. Buy the profile here.
Description
The project is being developed and currently owned by Apex Bethel Energy Center. The company has a stake of 100%.
It is a Gas Turbine power plant.
The project will generate 30,000MWh of electricity.
Development status
The project construction is expected to commence from 2024. Subsequent to that it will enter into commercial operation by September 2025.
Contractors involved
APEX Bethel Gas Fired Power Plant (APEX Bethel Gas Fired Power Plant Unit I) will be equipped with Dresser-Rand D-R EA-418 gas turbines. The phase consists of 2 gas turbines with 158.5MW nameplate capacity.
Ethos Energy Group is expected to perform operations and maintenance for thermal power project for a period of 3 years.