Bacabachi Solar PV Park is a 257.3MW solar PV power project. It is located in Sonora, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2019 and subsequently entered into commercial operation in January 2020. Buy the profile here.
Description
The project is developed and owned by Kenergreen SAPI de CV.
Bacabachi Solar PV Park is a ground-mounted solar project which is spread over an area of 588.6 hectares.
The project generates 435,354.48MWh electricity and supplies enough clean energy to power 214,000 households. The project cost is $363.897m.
2,114 inverters have been installed at the project site.
Development status
The project construction commenced in 2019 and subsequently entered into commercial operation in January 2020.
Contractors involved
Grupo Ortiz was selected to render engineering procurement construction services for the solar PV power project.
JinkoSolar Holding was selected as the supplier of the PV modules for the project. The company supplied modules with rated capacity of 380W.
The project is utilising single axis trackers supplied by Gonvarri Steel Services.
Grupo Ortiz is the O&M contractor for the solar PV power project for a period of 20 years.