Beatrice Combined Cycle Power Plant is a 250MW gas fired power project. It is located in Nebraska, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in January 2005. Buy the profile here.

Description

The project is currently owned by Nebraska Public Power District.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Northern Natural Gas Tallgrass.

The project generated 167,490MWh of electricity.

Development status

The project got commissioned in January 2005.

Contractors involved

TIC – The Industrial and Utility Engineering were selected to render engineering procurement construction services for the gas fired power project.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of 7E.03 gas turbines, each with 80MW nameplate capacity.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of ST6 steam turbine with 90MW nameplate capacity.

GE Power supplied electric generator for the project.

GE Power supplied electric generator for the project.

GE Power supplied electric generator for the project.

GE Power supplied electric generator for the project.

Vogt Power International supplied steam boiler for the project.

Vogt Power International supplied steam boiler for the project.

For more details on Beatrice Combined Cycle Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.