Belesar III is a 215MW hydro power project. It is planned on Mino river/basin in Galicia, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the announced stage. It will be developed in a single phase. The project construction is likely to commence in 2026 and is expected to enter into commercial operation in 2029. Buy the profile here.
Description
The project is being developed and currently owned by Naturgy Energy Group.
The project is expected to generate 9 GWh of electricity.
The hydro power project consists of 2 turbines, each with 107.5MW nameplate capacity.
The project has 2 electric generators that will be installed at the project site.
Development status
The project construction is expected to commence from 2026. Subsequent to that it will enter into commercial operation by 2029.
For more details on Belesar III, buy the profile here.
About Naturgy Energy Group
Naturgy Energy Group SA (Naturgy), formerly Gas Natural Fenosa, is an integrated gas and electric utility that carries out the exploration, development, liquefaction, regasification, transportation, storage, distribution and commercialization of natural gas. The company also undertakes the generation, distribution and commercialization of electricity. It carries out power generation through combined cycle, thermal, nuclear, hydro, co-generation and wind farm plants, and other special regime technologies. It has electricity generation operations in Mexico, Costa Rica, Dominican Republic, Panama, Chile, Brazil, Puerto Rico and Australia. The company has its operations in the Americas, Europe, Africa, Asia and Oceania. Naturgy is headquartered in Barcelona, Spain.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.