Benghazi North Combined Cycle Power Plant is a 915MW gas fired power project. It is located in Benghazi, Libya. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1995. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Benghazi North Combined Cycle Power Plant

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by General Electricity Company Of Libya with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel Oil.

The project generated 4,604,959MWh of electricity.

Development status

The project got commissioned in 1995.

Contractors involved

ACESCo and GE Power were selected to render engineering procurement construction services for the gas fired power project.

Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase I) is equipped with GE Power GT13E1 gas turbines. The phase consists of 3 gas turbines with 150MW nameplate capacity.

Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase II) is equipped with GE Power GT13E2 gas turbine. The phase consists of 1 gas turbine with 165MW nameplate capacity.

Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase III) is equipped with Fuji Electric Non-reheat, Condensing steam turbines. The phase consists of 2 steam turbines with 150MW nameplate capacity.

GE Power supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase I).

GE Power supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase I).

GE Power supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase II).

GE Power supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase II).

Fuji Electric supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase III).

Fuji Electric supplied electric generator for the Benghazi North Combined Cycle Power Plant (Benghazi North Combined Cycle Power Plant Phase III).

GE Power supplied steam boiler for the project.

GE Power supplied steam boiler for the project.

For more details on Benghazi North Combined Cycle Power Plant, buy the profile here.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.