The Bismayah Combined Cycle Power Plant IWPP is 4,580MW dual-fuel fired power project. It is planned in Baghdad, Iraq. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2017. Buy the profile here.
Description
The project is being developed and currently owned by Mass Group Holding.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant can run on dual-fuel. The primary fuel being used to power the plant will be natural gas. In case of shortage of natural gas the plant will run on Diesel.
The project cost is expected to be around $3,000m.
Development status
Post completion of the construction, the project is expected to get commissioned in 2017.
Power purchase agreement
The power generated from the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase III) will be sold to Ministry of Electricity, Iraq under a power purchase agreement for a period of 20 years.
Contractors involved
Avax is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) project. Avax is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)) project. ENKA Insaat ve Sanayi is expected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)) project.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)) will be equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)) will be equipped with GE Power D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)) will be equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)) will be equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)) will be equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)) will be equipped with GE Power D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) will be equipped with GE Power 2x1 MS 9F.03 gas turbines. The phase consists of 2 gas turbines with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) will be equipped with GE Power 2x1 MS D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) will be equipped with GE Power 2x1 MS 9F.03 gas turbines. The phase consists of 2 gas turbines with 260MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) will be equipped with GE Power 2x1 MS D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase III) will be equipped with GE Power 9F.04 gas turbines. The phase consists of 4 gas turbines.
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)).
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)).
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)).
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)).
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)).
GE Power is expected to be the supplier of electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)).
John Cockerill Group is likely to be the supplier of steam boiler for the project.
GE Power is expected to perform operations and maintenance for thermal power project for a period of 20 years.
For more details on Bismayah Combined Cycle Power Plant IWPP, buy the profile here.
About Mass Group Holding
Mass Group Holding Ltd (Mass Group) is a diversified company. The company business segments include power generation of electricity, cement production, steel and iron production. The company’s power generation segment offers power stations, gas power stations and wind power stations operations, management and development services. Its cement production segment offers ordinary, sulfate resistance cement and others. Mass Group’s steel and iron production segment manufactures industrial steel products, treatment furnaces and others. The company has operations in in Jordan and Iraq. Mass Group is headquartered in Amman, Jordan.