Blue Water is a 59.2MW onshore wind power project. It is located in Ontario, Canada. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2013 and subsequently entered into commercial operation in July 2014. Buy the profile here.

Description

The project was developed by Varna Wind. Cordelio Power and Axium Infrastructure are currently owning the project having ownership stake of 51% and 49% respectively.

The project supplies enough clean energy to power 15,000 households. The project cost is $144.626m.

The Tubular Steel towers installed at the project site are 80m high.

Development status

The project is currently active. The project construction commenced in 2013 and subsequently entered into commercial operation in July 2014.

Power purchase agreement

The power generated from the project is sold to Independent Electricity System Operator under a power purchase agreement for a period of 20 years from 2014. The contracted capacity is 59.2MW.

Contractors involved

GE Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 37 units of 1.6-100 turbines, each with 1.6MW nameplate capacity.

For more details on Blue Water, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.