Boazzo is a 95MW hydro power project. It is located on Chiese river/basin in Trentino-Alto Adige, Italy. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Buy the profile here.

Description

The project is currently owned by Hydro Dolomiti Enel.

Boazzo is a reservoir based project. The gross head of the project is 563.5m. The project generated 148 GWh of electricity.

The project has 2 electric generators installed at the site.

Contractors involved

Ansaldo Energia was selected as the turbine supplier for the hydro power project. The company provided 2 units of pelton turbines, each with 47.3MW nameplate capacity.

For more details on Boazzo, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.