Bogazkoy Combined Cycle Power Plant is a 390MW gas fired power project. It is located in Istanbul, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Buy the profile here.

Description

The project is developed and owned by Dogal Enerji Uretim. The company has a stake of 100%.

It is a CCGT with Cogen power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel. The fuel is procured from BOTAS.

The Gas fired project consists of 1 steam turbine with 140MW nameplate capacity.

Contractors involved

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of 9E gas turbines, each with 125MW nameplate capacity.

For more details on Bogazkoy Combined Cycle Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.