Bonete III Solar PV Park is a 46.42MW solar PV power project. It is planned in Castile-La Mancha, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2023 and is expected to enter into commercial operation in 2024. Buy the profile here.
Description
The project is being developed by Cobra Concesiones and is currently owned by Helios Energy Investments with a stake of 100%.
Bonete III Solar PV Park is a ground-mounted solar project which is planned over 90.5 hectares.
The project cost is expected to be around $32.262m.
The solar power project consists of 136,530 modules, each with 340W nameplate capacity.
2 inverters are likely to get installed at the project site.
9 inverters are likely to get installed at the project site.
Development status
The project construction is expected to commence from 2023. Subsequent to that it will enter into commercial operation by 2024.
Contractors involved
Cobra Concesiones is expected to render engineering procurement construction services for the solar PV power project.
For more details on Bonete III Solar PV Park, buy the profile here.