Bratislava Combined Cycle Power Plant is a 217.7MW gas fired power project. It is located in Bratislava, Slovakia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in August 1998. Buy the profile here.

Description

The project is currently owned by PPC Power.

It is a CCGT with Cogen power plant that is used for Baseload. The fuel is procured from Slovensky Plynarensky Priemysel, a.s..

The Gas fired project consists of 1 steam turbine with 60MW nameplate capacity.

Development status

The project got commissioned in August 1998.

Power purchase agreement

The power generated from the project is sold to Slovenske elektrarne under a power purchase agreement.

Contractors involved

Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SGT5-2000E gas turbine with 157.7MW nameplate capacity.

SES Tlmace supplied steam boiler for the project.

SES Tlmace supplied steam boiler for the project.

For more details on Bratislava Combined Cycle Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.